Current projects

    • 363 Lillie project [30 mid luxury apartment in Fulham with underground basement for car park –  
    • . Completion date: 08/06/2018
    • 363-365 Clapham Road project [28 mid luxury apartment, ground and basement office complex including a refurb of a great 2 listed building –  Start date: 12/02/2018. Duration: 75 weeks
    • Stratford Office Village [120 mid luxury apartment in three cores in Stratford with office complex and UKPN sub-station . Project start date: 13/08/2018 – Demolition and enabling works. Duration: 128 weeks